When you create a new project in P6 the default Percent Complete Type is Duration. Is this the best option and do you understand the difference between Duration, Physical and Units Percent Complete?

It is my opinion the this should always be changed to Physical for several reasons.

Click on this link>>> to read an article on P6 percent Complete Types and how they calculate.