Oracle Primavera P6 Version 21 Date Picker Box Enhancement

1          Introduction

In P6 Version 20 and earlier users could not see the time when setting a date when the User Preferences were set not to show the time. Often when setting an Actual Start of Finish date, Suspend or Resume date, constraints dates etc. P6 would pick an irrelevant time such as midnight. This is because P6 does not have the feature of Default Start time or Default Finish time found in other products like Microsoft Project.

2          Issues Created by not seeing the time when setting a date

As a result:

  • Actual dates were set at midnight and one day activities had a zero actual duration,
  • Suspend dates were set at the beginning of the day and not the end and Resume dates were set and the end of the day not the start of the day and
  • Constraints were set at midnight, so there was one extra day of negative float.
  • Project Must Finish dates were set at midnight allowing one day less for the project.

3          P6 Version 21 Date Picker Enhancement

P6 Version 21 introduced a function titled Users may See and Set Activity Start and Finish Times in the Date Picker box when the User Preferences are set only to show the date.

This function allows the user to see the time when setting a date even when the User Preferences are not set to show the time.

4          P6 Version 20 and earlier the time is not available

The picture below shows in P6 Version 20 and earlier the time is not displayed when setting a date:

Oracle Primavera P6 PPM Professional Date Picker Version 20 and earlier

Oracle Primavera P6 PPM Professional Date Picker Version 20 and earlier

5          P6 Version 21 the time may be set from the Date Picker box.

The picture below shows in P6 Version 21 that the time is now displayed when setting a date:

Oracle Primavera P6 PPM Professional Date Picker Version 21

Oracle Primavera P6 PPM Professional Date Picker Version 21

6          Authors Comments

This is a great enhancement as P6 usually picks the wrong time when setting Actual dates, Constraints, Suspend and Resume dates when the time is not set to be displayed from the User Preferences.

But, I still recommend that users should always display the time when editing a schedule, so they are able to see if activities are not starting at the start of the day of finishing at the end of the day.

A pdf of this article may be downloaded by clicking on this link: >>>>>>>>>>>

Paul E Harris

Director Eastwood Harris Pty Ltd

10 June 2022

99 Tricks and Traps for Oracle Primavera P6 PPM Professional Updated for Version 21 - The Casual Users Survival Guide

99 Tricks and Traps for Oracle Primavera P6 PPM Professional Updated for Version 21 – The Casual Users Survival Guide

Planning and Control Using Oracle Primavera P6 Versions 8 to 21 PPM Professional

Planning and Control Using Oracle Primavera P6 Versions 8 to 21 PPM Professional

SCHEDULING WITH SHIFTS IN PRIMAVERA P6

I am writing a new book titled 99 Tricks and Traps for Oracle Primavera P6 PPM Professional and this will be a Casual User’s “Survival Guide”. One of the new topics I will include in this book is scheduling with shifts.

The P6 inbuilt shift function is difficult to use and this article explains a simpler way to schedule with shifts in P6. Click on this link to read this article.

To see more explanations like this then please consider purchasing books by Paul Harris written on:

  • Microsoft Project,
  • Oracle Primavera P6 and
  • Elecosoft (Asta) Powerproject

These are available in many formats including paperback, spiral, Kobo, Kindle and iTunes.

These books are intended to be used:

  • As a self-teach book and user guide, or training course handouts.
  • Instructor PowerPoint slide shows are available and free pdf versions are supplied to educational organisations on request.

More information and links to sellers at this web site:

https://www.eh.com.au

Paul E Harris

Director Eastwood Harris Pty Ltd

Accelerate your understanding of scheduling software to advance your scheduling career and be able to prepare better schedules with Eastwood Harris books, online videos available through Udemy and training material on:

Details at  https://www.eh.com.au

Paul E Harris

Director Eastwood Harris Pty Ltd

 

Importing Activity Codes into Orical Primavera P6 using an XER file and Excel

The process outlined in this paper shows how you may simply edit an XER with Excel and import the Activity Codes, Click here for a link to this paper>>>

This new book is a casual users survival guide aimed at users who understand the software basics but require a short and snappy guide to demonstrate the less intuitive functions.

This book is available in pocket sized paperback and eBook formats from Kobo, Kindle and iTunes. Click here for more information>>>

Other books, training manuals and instructor PowerPoint slide shows by Paul Harris are available on:

  • Microsoft Project,
  • Oracle Primavera P6 and
  • Elecosoft (Asta) Powerproject

More information and links to sellers at our website>>>

Paul E Harris

Director Eastwood Harris Pty Ltd

99 Tricks and Traps for Oracle Primavera P6 PPM Professional

Accelerate your understanding of scheduling software to advance your scheduling career and be able to prepare better schedules with Eastwood Harris books, online videos available through Udemy and training material on:

Details at  https://www.eh.com.au

Paul E Harris

Director Eastwood Harris Pty Ltd

 

Primavera P6 Training Tips – How to Assign Activities to a WBS Node

Primavera P6 Training – Assigning Activities to WBS Nodesetting wbs activties1s

Activities are assigned to a WBS Node from the Activities Window.

They may be assigned using the following methods:

  • A new activity will inherit the WBS Node that is highlighted when an activity is created.
  • A new activity will inherit the WBS Node of a selected existing activity when the project is organized by WBS Nodes and an activity is created.
  • Select the activity and click the WBS box in the General tab in the lower window. This will open the Select WBS form where you may assign the WBS Node.
  • The  +  and the   –   are used to expand or roll up the WBS structure. Click on the  icon to assign the node.
  • Select one or more activities and move the mouse to the left of the activity description and the mouse will change into the shape displayed in the following picture. You may then drag the activities to another WBS Node.
setting wbs activties2


  • Insert the WBS column by clicking on the  icon and selecting WBS from the Columns form under General. Clicking in the WBS column of an activity will open the Select WBS form.

setting wbs activties3
Eastwood Harris Supplies Project Management Training Manuals, Project Management Training Presentations and Consulting on Primavera P6 and Microsoft Project 2010 across Australia.

Activity Types and Milestones in Primavera P6 Version 8.2

primavera p6 wbs activitiesActivity Types and Milestones in Primavera P6

An Activity may be assigned one of the following default Activity Types using the drop down box in the Project Defaults tab:

  • Finish Milestone
  • Level of Effort
  • Resource Dependent
  • Start Milestone
  • Task Dependent
  • WBS Summary
TASK TYPE DESCRIPTION
  • Task Dependent
These Activity Types have a duration and will only calculate the duration using the assigned calendar even when one or more resources are assigned to an activity.
  • Resource Dependent
These Activity Types have a duration and will calculate the duration only using the calendar assigned to the activity when NO resources are assigned to the activity.

These activities acknowledge Resource Calendars when resources are assigned.

This is similar to an Independent Activity Type in P3 and SureTrak.

They acknowledge the Activity calendar to calculate the Early Start date.

  • Level of Effort – LOE
This Activity type is similar to P3 and SureTrak Hammock activities. It spans from the start or finish of one or more predecessor activities to the start or finish of one or more successor activities which are linked by relationships.
  • Start Milestone
A Start Milestone has a start date and no finish date and is scheduled at the start of a time period and may not be assigned Resources.
  • Finish Milestone
A Finish Milestone has a finish date, no start date and is scheduled at the end of a time period and may not be assigned Resources.

Changing a milestone from Start to Finish would not affect a schedule when all the tasks are on one calendar but would move the milestone from the start of a day to the finish of the previous day.

  • WBS Summary
This Activity type calculates in the same way as P3 and SureTrak WBS activities and they span all activities with the same WBS code, but without relationships that are used with LOEs.
primavera p6 version 8-2 info button A Milestone has zero duration and is used to mark the start or finish of a major event. Primavera differentiates between Start and Finish Milestones in the same way as P3 and SureTrak, where a Start Milestone has a start date and no finish date and a Finish Milestone has a finish date and no start date. This is unlike Microsoft Project, which only has one type of Milestone. Later versions of Microsoft Project allow milestones with durations.

primavera p6 wbs activity types

Eastwood Harris Supplies Project Management Training Manuals, Project Management Training Presentations and Consulting on Primavera P6 and Microsoft Project 2010 across Australia.

Primavera P6 Training Tips Sydney – How to Open a New Project

project planning and control using primavera p6 version 8.2CREATING A NEW PROJECT IN PRIMAVERA P6

There are several methods to create a new project from the Projects Window:

  • Run the Create New Project wizard, or
  • Copy an existing project and edit it, or
  • Import a project created from another Primavera database or created with another software program such as P3, SureTrak or Microsoft Project, or Asta Powerproject.

Primavera P6 Enterprise Project Portfolio Management Version 8 Web has introduced project templates and dropped Methodology Manager/Project Architect.

Creating a Blank Project

You may create a new project at any point in time by selecting File, New…from the menu or clicking on the  icon on the Edit toolbar. You will be guided through the Create a New Project wizard which will require the following information:

  • The EPS Node the project is to be assigned to.
  • The Project ID, a code to represent the project (a maximum of 20 characters), and Project Name.
  • A Planned Start date, which is the earliest date any un-started activity will be scheduled to commence and an optional Project Must Finish By date.
    NOTE: Be sure to check the Start Time.
  • When a Project Must Finish By date is set the project float will be calculated to this date and not to the latest activity finish.

new project p6 tips

open new project in p6

  • The Responsible Manager is selected from the OBS structure. If the OBS has not been defined or the responsibility not assigned then Enterprise may be selected as the Responsible Manager.
  • The Resource Rate Type. Each resource may have five different rates. This is where the default rates are selected but may be changed after a resource has been assigned to an activity.

new project in p6Eastwood Harris Supplies Project Management Training Manuals, Project Management Training Presentations and Consulting on Primavera P6 and Microsoft Project 2010 across Australia.