NEW BOOK ON MICROSOFT PROJECT 365 and 2021, INCLUDING 2019, 2016 and 2013

Microsoft Project 2021 was released in October 2021 and Microsoft Project 365 is a subscription version of this software. This book is an update of the authors Microsoft Project 2019 book and has been written to be used as the basis of a two-day training course and includes updated exercises for the students to complete at the end of each chapter. This book will be available in paperback, spiral bound, Kindle, iTunes, Kobo and Google books. Unlike many training publications, this course book may then be used by the students as a reference book and instructor PowerPoint slide shows may also be purchased from Eastwood Harris Pty Ltd by clicking on this link>>>.

There are very few changes in the software but if you wish to read a short article titled What’s New In Microsoft Project 2021 listing the functional changes found by the author then click on this link>>>

Planning and Control Using Microsoft Project 365 and 2021- Including 2019, 2016 and 2013

Planning and Control Using Microsoft Project 365 and 2021- Including 2019, 2016 and 2013

UPDATING A MICROSOFT PROJECT SCHEDULE PROPERLY

A properly updated a schedule is very important if you wish to manage a project or substantiate delays with the schedule. It is very simple to update a Microsoft Project schedule incorrectly and end up with completed work in the future or incomplete work in the past, both of which are totally illogical. Download this article, which is an extract from my book Planning and Control Using Microsoft Project 2013, 2016 & 2019, that explains how a program is properly in Microsoft Project by clicking on this link>>>

SETTING PRIMAVERA P6 INDICATOR COLUMNS TO SHOW GOOD OR BAD VARIANCES

User Defined Fields has an Indicator option that allows four indicators to be displayed. These may be used in conjunction with a Global Change to indicate the status of an activity in respect to a Baseline.

If you wish to learn how to create a P6 Indicator column and set with a Global Chane then please read this article I have written by clicking on this link>>>.

Microsoft Project P6 Delay Analysis Techniques

Many construction contracts specify that a delay must be calculated from the critical path of a program.

Often project programs are completed Microsoft and therefore to demonstrate a delay the scheduler needs to add delays to the program to evaluate the delay.

If you wish to understand the various techniques of assigning delays to activities in Microsoft Project program, click on this link>>>.

Understanding how Microsoft Project Milestones are Calculated

 

Click on this link to read an article on how Microsoft Project Milestones calculate:

To see more explanations like this then please consider purchasing this Microsoft Project book by Paul Harris which is available in many formats, paperback, spiral, Kobo, Kindle and iTunes.

The book is intended to be used:

  • As a self-teach book and user guide, or a training manual for a two-day training course.
  • PowerPoint slide shows are available for training companies to purchase and pdf versions are available to educational organisations.

More information and links to sellers at this web site: https://www.eh.com.au/MSP2019.html

Published by Eastwood Harris Pty Ltd, Microsoft Project, Oracle Primavera P6 and Elecosoft Powerproject books and training material publishers.

https://www.eh.com.au