Project Management with Primavera P6 – Estimating or Planning for Control Sydney

primavare_P6 V82_training manualEstimating or Planning for Control Using Primavera P6 in Sydney

There are two modes that the software may use at Level 3:

  • Estimating – In this mode, the objective is to create a schedule with costs that are used only as an estimate. The schedule will never be updated. Activities may have many resources assigned to them to develop an accurate cost estimate and include many items that would never be updated in the process of updating a schedule.
  • Planning for Control – In this mode, the intention is to assign actual units (hours) and costs to resources, then calculate units and costs to completion, and possibly conduct an Earned Value analysis. In this situation, it is important to ensure that the minimum number of resources are assigned to activities, and preferably only one resource assigned to each activity. The process of updating a schedule in Sydney becomes extremely difficult and time consuming when a schedule has many resources per activity. The scheduler is then under threat of becoming a timekeeper and may lose sight of other important functions, such as calculating the forecast to complete and the project finish date.

The Balance Between the Number of Activities and Resources

When Planning for Control on large or complex schedules in Sydney, it is important to maintain a balance between the number of activities and the number of resources that are planned and tracked. As a rule, the more activities a schedule has, the fewer resources should be created and assigned to activities.

When a schedule contains a large number of activities and a large number of resources assigned to each activity, the result may be that no members of the project team are able to understand the schedule and the scheduler is unable to maintain it.

Instead of assigning individual resources, such as people by name, consider using “Skills” or “Trades,” and on very large projects use “Crews” or “Teams.”

This technique is not so important when you use a schedule for estimating the direct cost of a project (by assigning costs to the resources) or if you are not using the schedule to track a project’s progress (such as a schedule that is used to support written proposals).

Therefore, it is more important to minimize the number of resources in large schedules that will be updated regularly, because updating every resource assigned to each activity at each schedule update is very time consuming.