Default Percent Complete Type

The Default Percent Complete Type for each new activity in each project is assigned in the Defaults tab of the Details form in the Project Window:

default percent type in primavera 8.2

  • A new activity Percent Complete Type is set to the Default Percent Complete when created and may be changed at any time.

Percent Complete Types

  • Physical % Complete – This field enables the user to enter the percent complete of an activity and this value is independent of the activity durations. This is similar to the way P3 and SureTrak calculates the % Complete when the Link Remaining Duration and Percent Complete option is NOT selected.
  • Duration % Complete – This field is calculated from the proportion of the Original Duration and the Remaining Duration and they are linked. A change to one value will change the other. When the Remaining Duration is set to greater than the Original Duration this percent complete is always zero. This is similar to the way Primavera P3 and SureTrak calculates the % Complete when the Link Remaining Duration and Percent Complete option is selected
  • Units % Complete – This is where the percent complete is calculated from the resources’ Actual and Remaining Units. A change to one value will change the other and when more than one resource is assigned then all the Actual Units for all resources will be changed proportionally. This will be covered further in the Updating Resources chapter. This is similar to the Microsoft Project % Work Complete.

Activity % Complete

The Activity % Complete field is linked to the % Complete Type field assigned to an activity in the General tab of the Details form in the Activities Window or the % Complete Type column:

activity percent complete setting primavera 6

The Activity % Complete is also linked the % Complete Bar and this value is represented on the % Complete Bar.

percent complete bar primavera 6 8.2

Eastwood Harris Supplies Project Management Training Manuals, Project Management Training Presentations and Consulting on Primavera P6 and Microsoft Project 2010 across Australia.


Buy the Book Now Project Planning & Control Using Primavera P6