project planning and control using primavera p6 version 8.2CREATING A NEW PROJECT IN PRIMAVERA P6

There are several methods to create a new project from the Projects Window:

  • Run the Create New Project wizard, or
  • Copy an existing project and edit it, or
  • Import a project created from another Primavera database or created with another software program such as P3, SureTrak or Microsoft Project, or Asta Powerproject.

Primavera P6 Enterprise Project Portfolio Management Version 8 Web has introduced project templates and dropped Methodology Manager/Project Architect.

Creating a Blank Project

You may create a new project at any point in time by selecting File, New…from the menu or clicking on the  icon on the Edit toolbar. You will be guided through the Create a New Project wizard which will require the following information:

  • The EPS Node the project is to be assigned to.
  • The Project ID, a code to represent the project (a maximum of 20 characters), and Project Name.
  • A Planned Start date, which is the earliest date any un-started activity will be scheduled to commence and an optional Project Must Finish By date.
    NOTE: Be sure to check the Start Time.
  • When a Project Must Finish By date is set the project float will be calculated to this date and not to the latest activity finish.

new project p6 tips

open new project in p6

  • The Responsible Manager is selected from the OBS structure. If the OBS has not been defined or the responsibility not assigned then Enterprise may be selected as the Responsible Manager.
  • The Resource Rate Type. Each resource may have five different rates. This is where the default rates are selected but may be changed after a resource has been assigned to an activity.

new project in p6Eastwood Harris Supplies Project Management Training Manuals, Project Management Training Presentations and Consulting on Primavera P6 and Microsoft Project 2010 across Australia.